Construction Updates
100%
Site Mobilization
100%
Excavation
100%
Substructure
100%
Superstructure
98.71%
Masonry
67%
MEP 1st & 2nd Fix
9.63%
False Ceiling
35.86%
Wood Works
47.16%
Facade Works
68.41%
Floor Tile
94.62%
Plaster
33.96%
Painting
1.91%
MEP 3rd Fix
5.74%
External Works
0%
Handover