Construction Updates
100%
Site Mobilization
100%
Excavation
100%
Substructure
100%
Superstructure
99.90%
Masonry
87%
MEP 1st & 2nd Fix
81.92%
False Ceiling
53.24%
Wood Works
87.91%
Facade Works
98.03%
Floor Tile
98.79%
Plaster
48.21%
Painting
23.25%
MEP 3rd Fix
54.23%
External Works
0%
Handover