Construction Updates
100%
Site Mobilization
100%
Excavation
100%
Substructure
100%
Superstructure
98.68%
Masonry
59%
MEP 1st & 2nd Fix
8.26%
False Ceiling
32.54%
Wood Works
41.64%
Facade Works
53.79%
Floor Tile
22.82%
Painting
84.48%
Plaster
.76%
MEP 3rd Fix
0%
External Works
0%
Handover