Construction Updates
100%
Site Mobilization
100%
Excavation
100%
Substructure
100%
Superstructure
100%
Masonry
95.10%
MEP 1st & 2nd Fix
82.35%
False Ceiling
71.54%
Wood Works
94.21%
Facade Works
99.50%
Floor Tile
100%
Plaster
62.31%
Painting
56.53%
MEP 3rd Fix
88.23%
External Works
0%
Handover