Construction Updates
100%
Site Mobilization
100%
Excavation
100%
Substructure
88.47%
Superstructure
63.95%
Masonry
26%
MEP 1st & 2nd Fix
1.44%
False Ceiling
0.41%
Wood Works
0.12%
Facade Works
13%
Floor Tile
18.15%
Painting
46.36%
Plaster
.10%
MEP 3rd Fix
0%
External Works
0%
Handover