Construction Updates
100%
Site Mobilization
100%
Excavation
100%
Substructure
100%
Superstructure
100%
Masonry
99%
MEP 1st & 2nd Fix
97.43%
False Ceiling
79.51%
Wood Works
99.47%
Facade Works
100%
Floor Tile
100%
Plaster
73.25%
Painting
68.27%
MEP 3rd Fix
93.45%
External Works
0%
Handover